SOCO-IC-1187
220 MW storage in Wilkinson, GA · In queue since October 2023 · Proposed COD September 2027
220 MW
Capacity
1
Components
Battery
2y 7m
In Queue
IA Pending
IA Status
COD target: 2027
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-15
SOCO-IC-1187 is a proposed 220 MW battery storage project located in Wilkinson County, Georgia. The project, developed by Southern Company (SOCO), entered the Southern Company (SOCO) interconnection queue on October 26, 2023, with a proposed commercial operation date of September 15, 2027. The project's interconnection agreement (IA) status is currently listed as "IA Pending".
The development project consists entirely of battery storage, with a total capacity of 220 MW. The point of interconnection (POI) for the project is the Gordon Substation 115 kV Bus. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Wilkinson
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Gordon Substation 115 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.