SOCO-IC-1198
256 MW hybrid in Houston, GA · In queue since October 2023 · Proposed COD October 2025
256 MW
Capacity
2
Components
Solar + Battery
2y 7m
In Queue
IA Pending
IA Status
COD target: 2025
Total Duration
2 years
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-24
SOCO-IC-1198 is a proposed hybrid Solar+Battery project with a total capacity of 256 MW located in Houston County, Georgia. The development project, located in the Southeast region, consists of 128 MW of solar generation and a 128 MW battery energy storage system. The project is being developed by Southern Company (SOCO).
The project is currently in the Southern Company interconnection queue, with an entry date of October 31, 2023. The proposed commercial operation date is October 24, 2025, and the interconnection agreement (IA) status is currently listed as "IA Pending". The point of interconnection is the Robins AFB Solar Substation 115 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Houston
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Robins AFB Solar Substation 115 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1198