SOCO-IC-1207
200 MW hybrid in Decatur, GA · In queue since November 2023 · Proposed COD September 2026
200 MW
Capacity
1
Components
Battery
2y 6m
In Queue
IA Pending
IA Status
COD target: 2026
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
SOCO-IC-1207 is a proposed 200 MW hybrid solar and battery project located in Decatur County, Georgia. The development project, under the entity SOCO (Southern Company), consists of a 200 MW battery component.
The project is currently active in the Southern Company (SOCO) interconnection queue, with an entry date of November 30, 2023. Its proposed commercial operation date is September 1, 2026, and the interconnection agreement (IA) is currently pending. The point of interconnection (POI) is the Wiregrass Substation 230 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Decatur
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Wiregrass Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.