SOCO-IC-1222
250 MW storage in Bartow, GA · In queue since December 2023 · Proposed COD June 2027
250 MW
Capacity
1
Components
Battery
2y 5m
In Queue
IA Pending
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-14
SOCO-IC-1222 is a proposed 250 MW battery storage project located in Bartow County, Georgia. The project is being developed by Southern Company (SOCO) and consists entirely of battery storage. It is currently in the Southern Company interconnection queue, with an entry date of December 19, 2023. The proposed commercial operation date is June 14, 2027, and the interconnection agreement status is currently listed as "IA Pending". The point of interconnection is the Bowen SP 230 kV Bus.
The project is located in the Southeast region. As of the latest data, the project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
GA
County
Bartow
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Bowen SP 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.