Project SOCO-IC-1223 — Project Summary

Queue ID
SOCO-IC-1223
Capacity
250 MW
Technology
Battery
Status
active
Location
Hall, GA
Region
Southeast
Developer
IA Status
IA Pending

SOCO-IC-1223

SOCO-IC-1223BetaActiveBatterySOCOLBNL

250 MW storage in Hall, GA · In queue since December 2023 · Proposed COD February 2028

250 MW

Capacity

1

Components

Battery

2y 5m

In Queue

IA Pending

IA Status

COD target: 2028

Interconnection

Total Duration

4y 2m

In Study38%
Queue EntryDec 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-02-25

About

SOCO-IC-1223 is a proposed 250 MW battery storage project located in Hall County, Georgia. The project, developed by Southern Company (SOCO), entered the SOCO interconnection queue on December 19, 2023, with a proposed commercial operation date of February 25, 2028. Its interconnection agreement status is currently listed as "IA Pending."

The project will interconnect at the South Hall Substation 230 kV Bus. The development has appeared in recent news coverage regarding Southern Company's planned investments in energy storage.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Hall

Grid Region

Southeast

Market

Developer

Utility

Southern Company

Entity

SOCO

Service Type

Point of Interconnection

South Hall Substation 230 kV Bus

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SOCO-IC-1223