SOCO-IC-1229
300 MW hybrid in Coffee, GA · In queue since January 2024 · Proposed COD May 2026
300 MW
Capacity
2
Components
Solar + Battery
2y 4m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
2y 4m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
SOCO-IC-1229 is a proposed 300 MW hybrid solar and battery project located in Coffee County, Georgia. The development project, filed by Southern Company (SOCO), consists of a 200 MW solar component and a 100 MW battery energy storage system.
The project is currently in the Southern Company (SOCO) interconnection queue with an entry date of January 8, 2024. Its proposed commercial operation date is May 1, 2026, and its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Douglas - Kettle Creek Primary 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Coffee
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Douglas - Kettle Creek Primary 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1229