SOCO-IC-1233
300 MW hybrid in Irwin, GA · In queue since January 2024 · Proposed COD December 2026
300 MW
Capacity
2
Components
Solar + Battery
2y 4m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-04
The proposed SOCO-IC-1233 project is a 300 MW hybrid solar and battery energy storage development in Irwin County, Georgia. The project, located in the Southeast region, is being proposed by Southern Company (SOCO). It consists of a 200 MW solar array coupled with a 100 MW battery energy storage system.
The project is currently active in the Southern Company (SOCO) interconnection queue, with an entry date of January 8, 2024. The proposed commercial operation date is December 4, 2026. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the North Tifton - Stump Creek 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Irwin
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Tifton - Stump Creek 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1233