SOCO-IC-1246
86 MW hybrid in Liberty, GA · In queue since February 2024 · Proposed COD February 2026
86 MW
Capacity
2
Components
Solar + Battery
2y 3m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
2 years
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-09
SOCO-IC-1246 is a proposed 86 MW hybrid solar and battery project located in Liberty County, Georgia. The development project, which consists of 43 MW of solar and 43 MW of battery storage, is being proposed by Southern Company (SOCO).
The project is currently in the Southern Company interconnection queue (SOCO-IC) with an entry date of February 7, 2024. The proposed commercial operation date is February 9, 2026, and the interconnection status is currently in the Cluster Study phase. The point of interconnection is the Fort Stewart CU 115 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Liberty
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Fort Stewart CU 115 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1246