SOCO-IC-1251
157 MW generation in Lee, AL · In queue since March 2024 · Proposed COD April 2028
157 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
SOCO-IC-1251 is a proposed solar generation project with a total capacity of 157 MW, located in Lee County, Alabama, within the Southeast region. The project is being developed by SOCO, a subsidiary of Southern Company. It entered the Southern Company (SOCO) interconnection queue on March 14, 2024, with a proposed commercial operation date of April 1, 2028. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Bartlett's Ferry - West Point 115 kV Line.
The proposed project consists solely of solar photovoltaic generation, with the entire 157 MW capacity attributed to solar technology. The project is currently listed as active within the interconnection queue.
Generated from interconnection queue and public data sources
State
AL
County
Lee
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Bartlett's Ferry - West Point 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.