SOCO-IC-1257
722 MW generation in Bartow, GA · In queue since March 2024 · Proposed COD May 2029
722 MW
Capacity
1
Components
Gas
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-01
SOCO-IC-1257 is a proposed 722 MW gas-fired generation project located in Bartow County, Georgia. The project is being developed by Southern Company (SOCO) and is interconnected to the Plant Bowen Substation 500 kV Bus.
The project entered the Southern Company (SOCO) interconnection queue on March 18, 2024, with a proposed commercial operation date of May 1, 2029. Its interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
GA
County
Bartow
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Plant Bowen Substation 500 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1257