SOCO-IC-1258
722 MW generation in Bartow, GA · In queue since March 2024 · Proposed COD September 2029
722 MW
Capacity
1
Components
Gas
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2029
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
SOCO-IC-1258 is a proposed generation project located in Bartow County, Georgia. The project, with a total capacity of 722 MW, is being developed by Southern Company (SOCO). The project consists of 722 MW of gas-fired generation.
The project is currently in the Southern Company (SOCO) interconnection queue with an entry date of March 18, 2024. Its proposed commercial operation date is September 1, 2029. The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the Plant Bowen Substation 500 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Bartow
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Plant Bowen Substation 500 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.