SOCO-IC-1266
200 MW generation in Bullock, AL · In queue since March 2024 · Proposed COD November 2027
200 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-19
SOCO-IC-1266 is a proposed solar generation project located in Bullock County, Alabama. The project, with a total capacity of 200 MW, is being developed by Southern Company (SOCO). It consists of 200 MW of solar photovoltaic generation.
The project is currently in the Southern Company (SOCO) interconnection queue with an entry date of March 22, 2024. Its proposed commercial operation date is November 19, 2027, and its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Thurlow Dam - Union Springs 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Bullock
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Thurlow Dam - Union Springs 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.