SOCO-IC-1267
57.5 MW storage in Floyd, GA · In queue since March 2024 · Proposed COD March 2026
57.5 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
2 years
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-30
SOCO-IC-1267 is a proposed 57.5 MW battery storage project located in Floyd County, Georgia. The project, developed by Southern Company (SOCO), entered the SOCO interconnection queue on March 22, 2024, with a proposed commercial operation date of March 30, 2026. Its interconnection status is currently in the Cluster Study phase.
The project consists entirely of battery storage, with a total capacity of 57.5 MW. The point of interconnection is the Hammond SP Substation 230 kV Bus. This proposed project has appeared in recent news coverage regarding Southern Company's grid modernization efforts.
Generated from interconnection queue and public data sources
State
GA
County
Floyd
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Hammond SP Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1267