SOCO-IC-1271
530 MW storage in Cherokee, GA · In queue since March 2024 · Proposed COD January 2026
530 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
1y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-16
SOCO-IC-1271 is a proposed battery storage project located in Cherokee County, Georgia, within the Southeast region. The development project, with a total capacity of 530 MW, is being pursued by Southern Company (SOCO). It consists entirely of battery storage.
The project is currently active in the Southern Company (SOCO) interconnection queue as of March 27, 2024, with a proposed commercial operation date of January 16, 2026. Its interconnection status is listed as "Cluster Study," and the point of interconnection is the McGrau Ford Substation 230 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Cherokee
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
McGrau Ford Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1271