SOCO-IC-1272
200 MW storage in Paulding, GA · In queue since March 2024 · Proposed COD April 2027
200 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
SOCO-IC-1272 is a proposed 200 MW battery storage project located in Paulding County, Georgia. The project, under development by Southern Company (SOCO), entered the Southern Company (SOCO) interconnection queue on March 27, 2024, with a proposed commercial operation date of April 1, 2027. Its interconnection status is currently in the Cluster Study phase.
The project consists of a single 200 MW battery component. The point of interconnection is the McConnell - Pegamore 230 kV Line. The project has appeared in recent news coverage regarding Southern Company's planned grid investments.
Generated from interconnection queue and public data sources
State
GA
County
Paulding
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
McConnell - Pegamore 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1272