SOCO-IC-1276
300 MW hybrid in Mitchell, GA · In queue since April 2024 · Proposed COD July 2028
300 MW
Capacity
2
Components
Solar + Battery
2y 1m
In Queue
Cluster Study
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-28
SOCO-IC-1276 is a proposed 300 MW hybrid solar and battery project located in Mitchell County, Georgia. The development project, consisting of 150 MW of solar capacity and 150 MW of battery storage, is being proposed by Southern Company (SOCO).
The project is currently in the Southern Company interconnection queue with an entry date of April 1, 2024. Its proposed commercial operation date is July 28, 2028, and its interconnection agreement status is listed as "Cluster Study". The point of interconnection is the Mitchell Substation 230 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Mitchell
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Mitchell Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-1276