SOCO-IC-1280
15 MW storage in Floyd, GA · In queue since April 2024 · Proposed COD October 2027
15 MW
Capacity
1
Components
Battery
2y 1m
In Queue
IA Pending
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
SOCO-IC-1280 is a proposed 15 MW battery storage project located in Floyd County, Georgia. The project is being developed within the Southern Company (SOCO) service area. It entered the SOCO interconnection queue on April 15, 2024, with a proposed commercial operation date of October 1, 2027. Its interconnection agreement (IA) status is currently listed as "IA Pending".
The project consists of a single 15 MW battery component. The point of interconnection (POI) is the Judy Mountain - Mohawk Industries 115 kV Line. The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
GA
County
Floyd
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Judy Mountain - Mohawk Industries 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.