SOCO-IC-441
188.93 MW generation in Decatur, GA · In queue since February 2016 · Proposed COD May 2028
188.93 MW
Capacity
1
Components
Solar
10y 3m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
12y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-01
SOCO-IC-441 is a proposed solar generation project with a total capacity of 188.93 MW, located in Decatur County, Georgia. The project is listed in the Southern Company (SOCO) interconnection queue, with an entry date of February 25, 2016. The proposed commercial operation date is May 1, 2028. The interconnection agreement (IA) for the project has been executed.
The point of interconnection (POI) for SOCO-IC-441 is the Farley - South Bainbridge 230 kV Line. The developer is listed as SOCO.
Generated from interconnection queue and public data sources
State
GA
County
Decatur
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Farley - South Bainbridge 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-441