SOCO-IC-503
80 MW generation in Oglethorpe, GA · In queue since September 2016 · Proposed COD March 2020
80 MW
Capacity
1
Components
Solar
9y 8m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
3y 6m
Schedule
75 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-03-01
SOCO-IC-503 is a proposed solar generation project with a total capacity of 80 MW, located in Oglethorpe County, Georgia. The project is in the Southern Company (SOCO) interconnection queue, with an interconnection request date of September 21, 2016. The proposed commercial operation date is March 1, 2020, and the interconnection agreement has been executed. The point of interconnection is the East Watkinsville - Russell Dam (USA) 230 kV Line.
The development project is listed as active in the interconnection queue. It consists of 80 MW of solar photovoltaic generation. The project is located in the Southeast region.
Generated from interconnection queue and public data sources
State
GA
County
Oglethorpe
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
East Watkinsville - Russell Dam (USA) 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-503