SOCO-IC-694
615 MW generation in Sumter, GA · In queue since May 2018 · Proposed COD April 2023
615 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
4y 11m
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-04-01
SOCO-IC-694 is a proposed solar generation project with a total capacity of 615 MW. The project is located in Sumter County, Georgia, within the Southeast region, and is being developed by Southern Company (SOCO). It consists of 615 MW of solar photovoltaic generation.
The project is currently active in the Southern Company (SOCO) interconnection queue, with an initial queue entry date of May 3, 2018. The proposed commercial operation date is April 1, 2023, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the Fortson - North Tifton 500 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Sumter
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Fortson - North Tifton 500 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.