SOCO-IC-695
250 MW generation in Sumter, GA · In queue since May 2018 · Proposed COD April 2023
250 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
4y 11m
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-04-01
The proposed SOCO-IC-695 project is a 250 MW solar generation facility in Sumter County, Georgia. The project is being developed by SOCO, a subsidiary of Southern Company. It consists of 250 MW of solar photovoltaic generation.
The project is in the Southern Company (SOCO) interconnection queue, with an original queue entry date of May 3, 2018. The proposed commercial operation date is April 1, 2023, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the Fortson - North Tifton 500 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Sumter
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Fortson - North Tifton 500 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-695