SOCO-IC-759
40 MW generation in Burke, GA · In queue since December 2018 · Proposed COD May 2023
40 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
4y 5m
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-05-01
SOCO-IC-759 is a proposed 40 MW solar generation project located in Burke County, Georgia. The project is being developed by SOCO, a subsidiary of Southern Company. It consists of 40 MW of solar photovoltaic generation.
The project is in the Southern Company (SOCO) interconnection queue with an entry date of December 6, 2018. The proposed commercial operation date is May 1, 2023, and the interconnection agreement has been executed. The point of interconnection is the Sylvania - Waynesboro Primary 115 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Burke
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Sylvania - Waynesboro Primary 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-759