SOCO-IC-775
290 MW hybrid in Mitchell, GA · In queue since February 2019 · Proposed COD October 2022
290 MW
Capacity
2
Components
Solar + Battery
7y 3m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
3y 8m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-10-15
SOCO-IC-775 is a proposed 290 MW hybrid solar and battery project located in Mitchell County, Georgia. The development project, consisting of 260 MW of solar capacity and 30 MW of battery storage, is being developed by Southern Company (SOCO).
The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of February 19, 2019, and a proposed commercial operation date of October 15, 2022. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Mitchell - Raccoon Creek 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Mitchell
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Mitchell - Raccoon Creek 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-775