SOCO-IC-798
150 MW generation in Macon, GA · In queue since July 2019 · Proposed COD July 2024
150 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
5 years
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-07-01
SOCO-IC-798 is a proposed solar generation project with a total capacity of 150 MW, located in Macon County, Georgia. The project is being developed by Southern Company (SOCO). It consists of 150 MW of solar photovoltaic generation.
The project is in the Southern Company (SOCO) interconnection queue, with an entry date of July 11, 2019. Its proposed commercial operation date is July 1, 2024, and the interconnection agreement has been executed. The point of interconnection is the North Americus - Perry 115 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Macon
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Americus - Perry 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-798