SOCO-IC-831
80 MW generation in Washington, AL · In queue since October 2019 · Proposed COD April 2026
80 MW
Capacity
1
Components
Solar
6y 7m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
6y 6m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-30
SOCO-IC-831 is a proposed 80 MW solar generation project located in Washington County, Alabama. The project is being developed by Southern Company (SOCO) and interconnected to the Bassett Creek - McIntosh 115 kV Line. It entered the Southern Company (SOCO) interconnection queue on October 17, 2019, with a proposed commercial operation date of April 30, 2026. The interconnection agreement status is currently listed as Suspended.
The project consists of 80 MW of solar photovoltaic generation capacity. It is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AL
County
Washington
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Bassett Creek - McIntosh 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-831