SOCO-IC-832
80 MW generation in Monroe, AL · In queue since October 2019 · Proposed COD June 2026
80 MW
Capacity
1
Components
Solar
6y 7m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
SOCO-IC-832 is a proposed solar generation project located in Monroe County, Alabama. The project, with a total capacity of 80 MW, is being developed by SOCO, a subsidiary of Southern Company. It consists of 80 MW of solar photovoltaic generation.
The project is currently in the Southern Company interconnection queue, with an entry date of October 17, 2019. The proposed commercial operation date is June 30, 2026. The interconnection agreement status is currently listed as Suspended. The point of interconnection is the Barry - Monroeville 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Monroe
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Barry - Monroeville 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.