SOCO-IC-839
200 MW hybrid in Sumter, GA · In queue since November 2019 · Proposed COD July 2027
200 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-07-31
SOCO-IC-839 is a proposed 200 MW hybrid solar and battery project located in Sumter County, Georgia. The project, under the purview of Southern Company (SOCO), entered the interconnection queue on November 15, 2019, and has a proposed commercial operation date of July 31, 2027. The interconnection point of contact is the North Americus - Palmyra 230 kV Line.
The project consists of 200 MW of solar capacity coupled with battery storage. Its interconnection agreement has been executed. The project is listed in the Southern Company interconnection queue.
Generated from interconnection queue and public data sources
State
GA
County
Sumter
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Americus - Palmyra 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-839