SOCO-IC-885
80 MW hybrid in Dallas, AL · In queue since July 2020 · Proposed COD June 2024
80 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 11m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
SOCO-IC-885 is a proposed 80 MW hybrid solar and battery project located in Dallas County, Alabama. The development project, under the utility Southern Company (SOCO), consists of 80 MW of solar capacity coupled with battery storage.
The project is currently active in the SOCO interconnection queue with an entry date of July 15, 2020. The proposed commercial operation date is June 1, 2024, and the interconnection agreement status is currently suspended. The point of interconnection is the North Selma - Selma #1 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Dallas
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Selma - Selma #1 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-885