SOCO-IC-897
160 MW hybrid in Coffee, AL · In queue since August 2020 · Proposed COD February 2025
160 MW
Capacity
2
Components
Solar + Battery
5y 9m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 6m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-01
SOCO-IC-897 is a proposed 160 MW hybrid solar and battery project located in Coffee County, Alabama. The development project, consisting of 80 MW of solar capacity and 80 MW of battery storage, is in the Southern Company (SOCO) interconnection queue with an entry date of August 14, 2020. The proposed commercial operation date is February 1, 2025.
The interconnection agreement (IA) status for SOCO-IC-897 is currently listed as Suspended. The point of interconnection (POI) is the South Enterprise Substation 115 kV Bus. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AL
County
Coffee
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
South Enterprise Substation 115 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-897