Project SOCO-IC-902 — Project Summary

Queue ID
SOCO-IC-902
Capacity
76 MW
Technology
Solar+Battery
Status
active
Location
Emanuel, GA
Region
Southeast
Developer
IA Status
Suspended

SOCO-IC-902

SOCO-IC-902BetaActiveSolarBatterySOCOLBNL

76 MW hybrid in Emanuel, GA · In queue since August 2020 · Proposed COD September 2023

76 MW

Capacity

1

Components

Solar

5y 9m

In Queue

Suspended

IA Status

COD target: 2023

Interconnection

Total Duration

3y 1m

Schedule

32 months past proposed COD

In Study38%
Queue EntryAug 26, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-30

About

SOCO-IC-902 is a proposed 76 MW hybrid solar and battery project located in Emanuel County, Georgia. The development project, consisting of 76 MW of solar capacity, is in the Southern Company (SOCO) interconnection queue with an entry date of August 26, 2020.

The proposed commercial operation date for SOCO-IC-902 is September 30, 2023. The interconnection agreement status is currently listed as Suspended. The point of interconnection is the Vidalia - Wadley Primary (Black) 230 kV Line.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Emanuel

Grid Region

Southeast

Market

Developer

Utility

Southern Company

Entity

SOCO

Service Type

Point of Interconnection

Vidalia - Wadley Primary (Black) 230 kV Line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SOCO-IC-902