SOCO-IC-908
220 MW generation in Turner, GA · In queue since October 2020 · Proposed COD June 2023
220 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Suspended
IA Status
COD target: 2023
Total Duration
2y 8m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-01
SOCO-IC-908 is a proposed solar generation project with a total capacity of 220 MW, located in Turner County, Georgia. The project is being developed by Southern Company (SOCO) and interconnected to the North Tifton - Pitts 230 kV Line.
The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of October 9, 2020. The proposed commercial operation date is June 1, 2023, and the interconnection agreement status is currently suspended.
Generated from interconnection queue and public data sources
State
GA
County
Turner
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Tifton - Pitts 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.