SOCO-IC-911
220 MW generation in Miller, GA · In queue since October 2020 · Proposed COD May 2025
220 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 7m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-01
SOCO-IC-911 is a proposed solar generation project with a total capacity of 220 MW, located in Miller County, Georgia. The developer is Southern Company (SOCO). The project is in the Southern Company interconnection queue (SOCO-IC) with a queue entry date of October 29, 2020, and a proposed commercial operation date of May 1, 2025. Its interconnection agreement (IA) status is currently listed as Suspended.
The point of interconnection (POI) for the project is the Farley - South Bainbridge 230 kV Line. The project has appeared in recent news coverage regarding solar development in the Southeast region.
Generated from interconnection queue and public data sources
State
GA
County
Miller
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Farley - South Bainbridge 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-911