SOCO-IC-915
160 MW hybrid in Autauga, AL · In queue since November 2020 · Proposed COD November 2024
160 MW
Capacity
2
Components
Solar + Battery
5y 6m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
4 years
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-01
SOCO-IC-915 is a proposed 160 MW hybrid Solar+Battery project located in Autauga County, Alabama. The development project, which is in the Southeast region, consists of 80 MW of solar capacity coupled with 80 MW of battery storage. The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of November 13, 2020, and a proposed commercial operation date of November 1, 2024. Its interconnection agreement (IA) status is currently listed as Suspended.
The point of interconnection (POI) for the project is the County Line Rd - Gaston 230 kV Line. The utility is Southern Company. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AL
County
Autauga
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
County Line Rd - Gaston 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-915