SOCO-IC-924
80 MW hybrid in Baldwin, AL · In queue since December 2020 · Proposed COD June 2025
80 MW
Capacity
1
Components
Solar
5y 5m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 6m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-15
SOCO-IC-924 is a proposed 80 MW hybrid solar and battery project located in Baldwin County, Alabama. The development project, consisting of 80 MW of solar generation, is in the Southern Company (SOCO) interconnection queue with an entry date of December 16, 2020. The proposed commercial operation date is June 15, 2025.
The interconnection agreement (IA) status for SOCO-IC-924 is currently listed as Suspended. The point of interconnection (POI) is the Beulah (Gulf) - Silverhill 230 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Baldwin
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Beulah (Gulf) - Silverhill 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.