SOCO-IC-925
80 MW hybrid in Houston, AL · In queue since December 2020 · Proposed COD June 2025
80 MW
Capacity
1
Components
Solar
5y 5m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
4y 6m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-06-15
SOCO-IC-925 is a proposed 80 MW hybrid solar and battery project located in Houston County, Alabama. The development project, consisting of 80 MW of solar capacity, is in the Southern Company (SOCO) interconnection queue with an entry date of December 16, 2020. The proposed commercial operation date is June 15, 2025, and the interconnection agreement has been executed.
The project will interconnect at the Farley - Pinckard 230 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Houston
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Farley - Pinckard 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN