SOCO-IC-929
158 MW hybrid in Escambia, AL · In queue since January 2021 · Proposed COD June 2024
158 MW
Capacity
2
Components
Solar + Battery
5y 4m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 5m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
SOCO-IC-929 is a proposed 158 MW hybrid solar and battery project located in Escambia County, Alabama. The development project, consisting of 79 MW of solar capacity and 79 MW of battery storage, is being proposed by Southern Company (SOCO).
The project is currently active in the SOCO interconnection queue with an entry date of January 14, 2021. The proposed commercial operation date is June 1, 2024, and the interconnection agreement status is currently listed as Suspended. The point of interconnection is the Atmore - Flomaton 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Escambia
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Atmore - Flomaton 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-929