SOCO-IC-932
380 MW hybrid in Glynn, GA · In queue since December 2020 · Proposed COD July 2024
380 MW
Capacity
2
Components
Solar + Battery
5y 5m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 7m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-31
SOCO-IC-932 is a proposed 380 MW hybrid solar and battery energy storage project located in Glynn County, Georgia. The project, developed by Southern Company (SOCO), consists of a 250 MW solar array coupled with a 130 MW battery energy storage system. It is interconnected to the Southern Company (SOCO) queue as of December 21, 2020, with a proposed commercial operation date of July 31, 2024. The interconnection agreement (IA) status is currently listed as Suspended.
The point of interconnection (POI) for the project is the Thalmann TS 230 kV Bus. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Glynn
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Thalmann TS 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-932