SOCO-IC-933
380 MW hybrid in Glynn, GA · In queue since December 2020 · Proposed COD February 2024
380 MW
Capacity
2
Components
Solar + Battery
5y 5m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-24
SOCO-IC-933 is a proposed 380 MW hybrid solar and battery project located in Glynn County, Georgia. The development project, located in the Southeast region, consists of a 250 MW solar component and a 130 MW battery energy storage system. The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of December 21, 2020, and a proposed commercial operation date of February 24, 2024.
The interconnection status for SOCO-IC-933 is currently listed as "Suspended." The point of interconnection is the Thalmann TS 230 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Glynn
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Thalmann TS 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.