SOCO-IC-942
1,600 MW hybrid in Glynn, GA · In queue since March 2021 · Proposed COD April 2025
1,600 MW
Capacity
2
Components
Solar + Battery
5y 2m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 1m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-14
SOCO-IC-942 is a proposed 1600 MW hybrid solar and battery project located in Glynn County, Georgia. The project, in the Southeast region, consists of 1200 MW of solar generation and 400 MW of battery energy storage. The developer is Southern Company (SOCO).
The project is currently active in the Southern Company (SOCO) interconnection queue, with an entry date of March 19, 2021. The proposed commercial operation date is April 14, 2025. The interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Thalmann TS 500 kV Bus.
Generated from interconnection queue and public data sources
State
GA
County
Glynn
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Thalmann TS 500 kV Bus
Data Source
LBNL