SOCO-IC-943
80 MW generation in Talladega, AL · In queue since March 2021 · Proposed COD April 2025
80 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 1m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-16
SOCO-IC-943 is a proposed solar generation project located in Talladega County, Alabama. The project, with a total capacity of 80 MW, is being developed within the Southern Company (SOCO) service area. It consists of 80 MW of solar photovoltaic generation.
The project is currently in the Southern Company interconnection queue (SOCO-IC-943), with an entry date of March 31, 2021. The proposed commercial operation date is April 16, 2025. The interconnection agreement (IA) status is currently listed as Suspended.
Generated from interconnection queue and public data sources
State
AL
County
Talladega
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Coosa Pines - Logan Martin Dam No. 2 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.