SOCO-IC-944
210 MW generation in Turner, GA · In queue since April 2021 · Proposed COD February 2026
210 MW
Capacity
1
Components
Solar
5y 1m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
4y 10m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-01
SOCO-IC-944 is a proposed solar generation project with a total capacity of 210 MW, located in Turner County, Georgia. The project is in the Southern Company (SOCO) interconnection queue, with an entry date of April 6, 2021, and a proposed commercial operation date of February 1, 2026. The point of interconnection is the North Tifton - Pitts 230 kV Line.
The interconnection agreement (IA) status for SOCO-IC-944 is currently listed as Suspended. The developer is listed as SOCO.
Generated from interconnection queue and public data sources
State
GA
County
Turner
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Tifton - Pitts 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-944