SOCO-IC-945
270 MW hybrid in Turner, GA · In queue since April 2021 · Proposed COD February 2026
270 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
4y 10m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-01
SOCO-IC-945 is a proposed 270 MW hybrid solar and battery project located in Turner County, Georgia. The development project, located in the Southeast region, consists of 210 MW of solar capacity coupled with a 60 MW battery energy storage system. The project is being proposed within the Southern Company (SOCO) interconnection queue, with an initial queue entry date of April 6, 2021.
The proposed commercial operation date for SOCO-IC-945 is February 1, 2026. As of the latest data, the project's interconnection agreement (IA) status is listed as Suspended. The point of interconnection (POI) is the North Tifton - Pitts 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Turner
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
North Tifton - Pitts 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-945