SOCO-IC-950
250 MW generation in Mcduffie, GA · In queue since April 2021 · Proposed COD June 2024
250 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-06-01
SOCO-IC-950 is a proposed 250 MW solar generation project located in McDuffie County, Georgia. The project, developed by Southern Company (SOCO), entered the SOCO interconnection queue on April 6, 2021, and has a proposed commercial operation date of June 1, 2024. The interconnection agreement (IA) for the project has been executed.
The point of interconnection (POI) for SOCO-IC-950 is the Thomson Primary Substation 230 kV Bus. The project consists of 250 MW of solar photovoltaic generation capacity.
Generated from interconnection queue and public data sources
State
GA
County
Mcduffie
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Thomson Primary Substation 230 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-950