SOCO-IC-964
150 MW hybrid in Emanuel, GA · In queue since June 2021 · Proposed COD July 2025
150 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 1m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-15
SOCO-IC-964 is a proposed 150 MW hybrid solar and battery project located in Emanuel County, Georgia. The development project, under the utility Southern Company (SOCO), consists of 150 MW of solar capacity. It is currently listed as active in the SOCO interconnection queue, with an initial queue entry date of June 9, 2021. The proposed commercial operation date is July 15, 2025.
The project's interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Vidalia - Wadley Primary (Black) 230 kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Emanuel
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Vidalia - Wadley Primary (Black) 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN