SOCO-IC-966
130 MW hybrid in Decatur, GA · In queue since June 2021 · Proposed COD July 2024
130 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-15
SOCO-IC-966 is a proposed 130 MW hybrid solar and battery project located in Decatur County, Georgia. The development project, under the utility Southern Company (SOCO), consists of 130 MW of solar capacity. It is listed as active in the SOCO interconnection queue as of June 9, 2021, with a proposed commercial operation date of July 15, 2024. The interconnection agreement status is currently suspended.
The point of interconnection for the proposed project is the South Bainbridge - Sub 20 (TAL) 230 kV Line. The project has appeared in recent news coverage regarding Southern Company's renewable energy developments.
Generated from interconnection queue and public data sources
State
GA
County
Decatur
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
South Bainbridge - Sub 20 (TAL) 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-966