160 MW hybrid in Lowndes, AL · In queue since July 2021 · Proposed COD June 2026
160 MW
Capacity
2
Components
Solar + Battery
4y 10m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
SOCO-IC-971 is a proposed 160 MW hybrid solar and battery project located in Lowndes County, Alabama. The development project, which is in the Southeast region, consists of 80 MW of solar capacity coupled with 80 MW of battery storage. The developer is Southern Company (SOCO).
The project is listed in the SOCO interconnection queue with an entry date of July 8, 2021. The proposed commercial operation date is June 1, 2026. The interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Greenville - Pintlala 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Lowndes
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Greenville - Pintlala 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.