SOCO-IC-973
250 MW hybrid in Jasper, GA · In queue since July 2021 · Proposed COD September 2024
250 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
SOCO-IC-973 is a proposed 250 MW hybrid solar and battery project located in Jasper County, Georgia. The project, under development by Southern Company (SOCO), consists of 250 MW of solar capacity. It is listed as active in the Southern Company (SOCO) interconnection queue with an entry date of July 14, 2021, and a proposed commercial operation date of September 1, 2024.
The interconnection agreement (IA) status for SOCO-IC-973 is currently listed as Suspended. The point of interconnection (POI) is the Eatonton Primary - Porterdale Primary 230 kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Jasper
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Eatonton Primary - Porterdale Primary 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.