SOCO-IC-979
160 MW hybrid in Conecuh, AL · In queue since August 2021 · Proposed COD September 2026
160 MW
Capacity
2
Components
Solar + Battery
4y 9m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
SOCO-IC-979 is a proposed 160 MW hybrid solar and battery project located in Conecuh County, Alabama. The development project, which is in the Southeast region, consists of 80 MW of solar capacity coupled with 80 MW of battery storage. The project is being developed within the Southern Company (SOCO) footprint.
The project is listed in the SOCO interconnection queue as of August 20, 2021, with a proposed commercial operation date of September 30, 2026. Its interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Evergreen _x0013_ Monroeville 115 kV Line.
Generated from interconnection queue and public data sources
State
AL
County
Conecuh
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Evergreen _x0013_ Monroeville 115 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-979