SOCO-IC-980
200 MW hybrid in Oglethorpe, GA · In queue since August 2021 · Proposed COD March 2024
200 MW
Capacity
2
Components
Solar + Battery
4y 9m
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
2y 7m
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-01
SOCO-IC-980 is a proposed 200 MW hybrid solar and battery energy storage project located in Oglethorpe County, Georgia. The development project, consisting of 100 MW of solar capacity and 100 MW of battery storage, is being proposed by Southern Company (SOCO).
The project is currently in the Southern Company interconnection queue with an entry date of August 26, 2021. The proposed commercial operation date is March 1, 2024, and the interconnection agreement status is currently listed as Suspended. The point of interconnection is the East Watkinsville - Russell Dam (USA) 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Oglethorpe
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
East Watkinsville - Russell Dam (USA) 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-980