250 MW generation in Lamar, MS · In queue since October 2021 · Proposed COD March 2025
250 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
3y 5m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
SOCO-IC-986 is a proposed solar generation project with a total capacity of 250 MW, located in Lamar County, Mississippi. The project is being developed within the Southern Company (SOCO) service area. It consists of 250 MW of solar photovoltaic generation.
The project is listed in the Southern Company interconnection queue (SOCO-IC-986) with an entry date of October 21, 2021. The proposed commercial operation date is March 1, 2025. The interconnection agreement (IA) status is currently listed as Suspended.
Generated from interconnection queue and public data sources
State
MS
County
Lamar
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Hattiesburg Southwest - Adams Creek 230 kV LIne
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.